On Target
The King Street widening project is on schedule as contractors
race toward an Aug. 6 deadline.
Frank Gioscio, resident engineer for the N.C. Department of
Transportation, said that, based on contract pay-outs as various stages of work are completed, the
project is on the fast track for its targeted completion date.
The project became a
priority when the state received federal stimulus funds this spring, with the goal of completing
the main work by the time the new Watauga High School opens for the fall semester in
2010.
"We're so new into the project, but if I had to say, we're probably right on
schedule," Gioscio said Tuesday. "Taking the percentage of what is paid to the contractor, we're
probably a little bit ahead."
The contract specifies stages that should be completed by
certain dates, and the contractor has a major financial stake in having all lanes open by the
deadline. The contractor will receive a bonus if the project routes all traffic in the final
traffic pattern from the N.C.105 Extension to NC 194 in Perkinsville by Aug. 6, but will be fined
each day after that if the project is late.
"There is a bonus clause and liquidated damage
clause," Gioscio said. "If they meet this deadline, the NCDOT will pay them a $300,000 incentive.
If they do not meet it, they will pay a penalty of $5,000 a day."
Gisocio said it's likely
that periphery work will continue past the deadline into next fall, but the major lanes should be
open.
"That doesn't mean it has to be totally complete--but they have to have it in the
final traffic pattern with all the lanes open," he said. The 1.1-mile widening has an estimated
price tag of $15.2 million.
The utility companies are also playing a role in the speed of
the project. "Blue Ridge Electric (Membership Corporation) is totally done," Gioscio said. "New
River Light & Power is ahead of schedule and doing everything they can to stay out of the way.
AT&T has the potential of slowing things down if they don't start moving poles for
us."
Many utility poles are shared and main poles are already installed, and a series of
"duct banks" will allow for utility connections that cross beneath the street. The project will
have 13 such banks, which will reduce the number of overhead wires and improve the skyline, a
request made by the Town of Boone.
On Sunday night, crews will close some lanes while they
are out in the road installing duct banks, but it shouldn't lead to major delays, Gioscio
said.
Meanwhile, major milestones are occurring on the U.S. 321 widening below Blowing
Rock. Three sections of passing lanes will be opening this week, which will help traffic flow.
Gioscio said there had been complaints about slow-moving trucks, especially with northbound
traffic heading up the mountain.
"We know we're going to be working on the project until
sometime next year, and we have had some public complaints," Gioscio said. "There will be two
areas for northbound traffic and one for southbound traffic (to pass). That's kind of a major
milestone for us, to open up part of the project for more than two lanes.
The project began
in 2005 and is already a year behind its original expected completion date. Gioscio said it would
likely be completed by summer.
The third phase of the widening between Caldwell County and
Blowing Rock, which passes through the Green Park Historic District and the downtown area, is
already a year behind before it even starts. Right-of-way purchases and negotiations are underway
for the third phase, which is scheduled for construction in 2011.
