|
Council, DOT discuss highway project
By Frank Ruggiero
Its a topic that offers a wide berth for discussion.
Seated at the table, from
left, NCDOT Division 11 construction engineer Trent Beaver,
district engineer Michael Poe and division maintenance
engineer Charles Reinhardt discuss traffic and road improvement
matters at a May 2 meeting with the Boone Town Council.
Photo by Frank
Ruggiero
|
A special meeting of the Boone Town Council with
N.C. Department of Transportation (DOT) officials offered questions
and answers about the U.S. 421 widening project.
The project would see the widening of U.S. 421 from Hardin Street
to N.C. 194, modifying the four-lane roadway to a six-lane divided
highway.
The 1.1 mile project weighs in at a grand total of $34.8 million,
including right of way acquisition and construction.
In the process, one residential property owner and 65 residential
tenants will be displaced, while on the business side, nine
business owners and 21 business tenants will be displaced.
Right of way acquisitions are still under way.
The DOT expects to award the project bid on April 21, 2009,
after which construction will begin.
This is a fairly significant project, considering its
just a little over a mile long, said Mike Pettyjohn, division
engineer of the DOTs Division 11.
Pettyjohn said engineers are pushing to finish the portion from
N.C. 194 to N.C. 105 Extension in 2010 to accommodate the opening
of the new Watauga High School in the Perkinsville area.
We cant guarantee well make that, but thats
what were gunning for, he said, adding that the
remainder of the project, from N.C. 105 Extension to Hardin
Street, should be completed by 2011-12.
Because of the areas short construction seasons, due mainly
to inclement weather, Pettyjohn said the DOT would try to complete
as much as possible on the first leg of work, so roadwork is
not in the way by the time the school opens.
We hope to have most of two construction seasons for that
first part, and the contractor may be able to work throughout
the project during this time, as well, but we plan to emphasize
the first part by stipulating intermediate completion times
in the contract, Pettyjohn later said.
Mayor pro tem Lynne Mason asked Pettyjohn if he anticipated
construction crews working day or night, and Pettyjohn said
to meet the schedule, they may need to work through both day
and night.
Probably, we may have to look at them trying to reduce
their time in the road during peak hours, but well pretty
much let them have it 24 hours a day to meet this schedule,
he said.
Trent Beaver, division construction engineer, said time restrictions
factor into total contract time Furthermore, the DOT would like
to meet with the town to discuss ways to minimize restrictions,
he said.
Council member Stephen Phillips asked if there are any plans
to help reroute traffic during the construction period, and
Pettyjohn said there really is no route with which to do so.
We know locals will reroute themselves somewhat, because
they know some of the local roads, but as far as directing out-of-state,
out-of-town people and trucks, there really is just no place
to go, Pettyjohn said.
In response to the towns inquiries about street lighting
for the entire project area, he said ornamental or decorative
lighting could be provided by the town, which would also be
responsible for power and maintenance cost.
Regarding sidewalks on both sides of the project, Pettyjohn
said they will be furnished with the state and town splitting
the cost 70/30 percent, respectively. Concerning bicycle lanes,
he said the outside lanes will be widened by two feet, boosting
the total width to 14 feet, to accommodate bicycle traffic.
N.C. Rep. Cullie Tarleton asked if the lanes would be marked
or striped to indicate a dedicated bicycle lane, and Pettyjohn
said that varies across the state. Since there is also two feet
of curb and gutter, the bicycle lanes should be four feet total,
the typical width of such a lane. The grates near the curb will
be angled to accommodate bicycle tires, Pettyjohn added.
As far as pedestrian crosswalks and intersection crossing heads
are concerned, Pettyjohn said crosswalks and signals will be
considered during the signal design phase, though crosswalks
will not be provided at non-signalized locations. Furthermore,
the DOT does not recommend a pedestrian signal between N.C.
105 and Hardin Street.
Concerning landscaping, Pettyjohn said the area between N.C.
194 and N.C. 105 Extension will be difficult, as there is not
much room to soften all the new concrete. Safety
is also a factor, in that a worker would need enough room to
maintain the greenery.
Depending on how much is planted, the town might also be required
to share in the cost of landscaping, he added, as well as being
responsible for its maintenance. Phillips stressed the importance
of proper landscaping on U.S. 421, as Boones economy is
tourism-based, and that stretch of road is visitors first
impression of the town.
In order to maintain the hotels perched on the ridge above the
highway, Pettyjohn said retaining walls would be required, and
the DOT is considering a two-tiered structure.
For the walls surface, he said the plan is to have architectural
surface treatment, in which the concrete is formed with a certain
design and color, both of which would be the towns choice.
The level between both tiers will likely be landscaped with
grass, as anything more substantial could prove troublesome
for maintenance.
Since the renovations will eventually remove left-turn access
to secondary streets between the N.C. 105 Extension and Hardin
Street, the town requested at least one controlled crossover,
preferably near Boone Public Works.
Due to minimum spacing requirement between the median crossovers,
however, Pettyjohn said the DOT would not be able to provide
left-turn access at that location.
|